A former Clearwater bank will find new life as a luxury condominium when it opens to residents next year.
The SkyView at 400 Cleveland St. is a collection of 51 condos designed by
Gomez Vazquez International Architects. The location was formerly the AmSouth bank building, and the complex will incorporate the original structure by reinforcing the steel and concrete framework initially designed to house the bank’s vault.
Construction on the project began in October 2014, and the first phase is nearly finished, according to Alvaro Gonzalez Guerra Gomez, the architecture firm's principal of North America. The firm has designed more than 200 lifestyle developments worldwide since it was founded in 1968, although this is the first in the Tampa Bay area.
The first phase entails "gutting and demolition of the existing facade, core of the building, stairwell and elevator shafts to make way for 38 units in place of the previous bank offices," Gonzalez says.
"This, of course, includes the amenities -- pool, fitness center, kids club, smoothie bar, and the vault room, which was transformed into a room where the condo owners can have cozy get-togethers."
Other amenities include a spa and an amenities deck with resort-style day beds and views of the Gulf of Mexico.
"It’s the ultimate escape and destination for relaxing and socializing," Gonzalez says.
All units will have two bedrooms and two bathrooms, Gonzalez says. The average size will be 1,300 square feet. Prices will range from $260,000 to $890,000 and depend on the view, the floor and the terrace space.
Although developers Moises and Cleman Agami decline to disclose their total investment in the project, Paulette Agami, design manager and spokeswoman, says they want to bring "a fresh, contemporary and chic architectural landmark" to Clearwater that features "an air of high design and clean lines."
"That’s precisely what was accomplished," she says. "When potential buyers or visitors walk into The SkyView showroom, there are, without fail, remarks about the good taste that we have brought downtown."
The entire project is expected to be complete in March 2017.